Page
1
of 39
Baltic Marine Environment
Protection Commission
HELCOM Guidelines for Management of Dredged Material at Sea
and
HELCOM Reporting Format for Management of Dredged Material at Sea
Adopted by HELCOM 36-2015 on 4 March 2015 and
amended by HELCOM 41-2020 on 4 March 2020
Katajanokanlaituri 6 B
Phone:
+358 207 412 649
E-mail:
firstname.lastname@helcom.fi
FI-00160 Helsinki
Web:
http://helcom.fi
secretariat@helcom.fi
Finland
Page
2
of 39
PREFACE
These Guidelines were adopted by HELCOM 36-2015 after the revision, in accordance with the 2013 IMO
London Protocol and London Convention Specific Guidelines for Assessment of Dredged Material. The
Contracting Parties should apply these guidelines in their authorisation or regulation procedures for dredged
material. However, the guidelines also contain recommendations that will not be applicable in all national or
local circumstances.
1. INTRODUCTION
1.1 Dredging is essential to maintain navigation to, in and from ports and harbours, for the development of
port facilities as well as for remediation, flood management and to maintain the carrying capacity of
marine and coastal systems. Much of the material removed during these necessary activities requires
deposit at sea. Most of the material dredged from within the Baltic Sea Area is, by its nature, either
uncontaminated or only slightly contaminated by human activity (i.e. at, or close to, natural background
levels). However, a smaller proportion of dredged material is contaminated to an extent that major
environmental constraints need to be applied when developing management options (cf. Section 7.
Management Options).
1.2 Dredged sediments are recognised as part of the natural sediment cycle. Therefore, when considering
suitable management options, it is generally the preferred option to retain dredged material within the
same aquatic sedimentary system from where it originated, if it is environmentally, technically, socially
and economically feasible to do so.
Overview of Dredging Activities
1.3 The different types of dredging activities are outlined below:
a. Dredging for water-based infrastructure, includes:
Capital (or new-work) dredging for navigation involves enlarging or deepening existing channel
and port areas or creating new ones; and for engineering purposes includes constructing trenches
for pipes, cables, immersed tube tunnels, and removal of material unsuitable for foundations or
for aggregate extraction, and for hydraulic purposes this involves increasing the flow capacity of
the waterway;
Maintenance dredging to maintain channels, berths or construction works, etc. at their designed
dimensions (i.e. to counteract sedimentation and changes in morphology);
Dredging for coastal protection: use of sediments for such activities as beach nourishment and
construction of levees, dykes, jetties, etc.
b. Dredging for the purposes of ecosystem enhancement:
Environmental dredging to remove contaminated sediment for the purpose of reducing risks to
the environment and to human health;
Restoration dredging to restore or create environmental features or habitats to establish
ecosystem functions, benefits, and services; e.g., wetlands creation, island habitat
construction/nourishment, construction of offshore reefs and topographic features for fisheries
enhancement, etc.; and
Dredging to support local and regional sediment processes retaining sediment within the natural
sediment system to support sediment-based habitats, shorelines, and infrastructure.
Page
3
of 39
2. SCOPE
1
2.1 The guidelines are designed to assist Contracting Parties in the management of dredged material in ways
that will prevent and eliminate pollution in accordance with Article 3 to the 1992 Helsinki Convention,
and protect marine species and habitats in the Baltic Sea Area in accordance with Article 15
2
. Dredged
materials have been listed in Regulation 1 of Annex V as being permitted to be dumped at sea, as an
exception from the general prohibition from dumping in Article 11 (1) of the Convention.
2.2 Any deposit into the maritime area of dredged materials, independently of whether it is considered as
dumpingor placement” within the Helsinki Convention (cf. Article 4(a) and Article 2(b)(ii) respectively),
should be assessed on a case-by-case basis in order to ensure that it complies with the objectives of the
Convention, as outlined in these Guidelines.
2.3 For the Contracting Parties that are also EU Member States, the Guidelines are conceived as a tool assisting
them in the management of dredged material that is subject to current European Directives (e.g. Water
Framework Directive 2000/60/EC, Marine Strategy Framework Directive 2008/56/EC, Natura2000 areas
under the Birds and Habitat Directives 2009/147/EC and 92/43/EEC). Also, the Directive 2008/98/EC of
the Parliament and of the Council of 19 November 2008 on waste, (hereinafter the Waste Framework
Directive), has been identified by Contracting Parties as having implications on the management of
dredged material. Which implications those are exactly, and how this affects national legislation, remains
in many cases unclear. Clarifications regarding the relationship between the existing national
interpretations in the application of the Waste Framework Directive to dredged material and the dredged
material management guidelines shared in HELCOM Area are provided in the technical background
document (cf. 14 REFERENCES).
2.4 The guidelines in particular address the management of dredged material in the maritime area,
subsequent to any dredging technique including hydrodynamic and sidecast dredging. In addition to
preventing and eliminating adverse effects the guidelines, where appropriate, seek to maintain or
enhance the existing environmental conditions and to create new opportunities.
2.5 The guidelines are primarily a scientific and technical framework for assessing dredged material proposed
for deposit at sea. While economic considerations are acknowledged, they are not dealt with in detail in
these guidelines. This implicates that the detailed procedures described in the guidelines will not be
applicable in all national or local circumstances.
2.6 In the context of these guidelines, dredged materials are deemed to be sediments or rocks with associated
water, organic matter etc. removed from areas that are normally or regularly covered by water, using
dredging or other excavation equipment.
2.7 It is recognised that both removal and deposit of dredged sediments may cause harm to the marine
environment. Contracting Parties are encouraged to exercise control over both dredging and dredged
material management using a Best Environmental Practice (BEP) approach designed to minimise both the
quantity of material that has to be dredged and the impact of the dredging and depositing activities in the
maritime area - see Technical Annex III. Contracting Parties are encouraged to develop regional dredged
material management plans in order to minimize the possible impacts and maximizing possible benefits
from dredging and depositing. Advice on environmentally acceptable dredging techniques is available
from a number of international organisations e.g. the Permanent International Association of Navigation
Congresses (PIANC), the European and Central Dredging Association (EuDA and CEDA).
2.8 The schematic shown in Figure 1 presents the steps involved in the application of these Guidelines where
important decisions should be made. In general, national authorities should use this schematic in an
1
All Article, Annex or Regulation references mentioned in this chapter refer to the 1992 HELCOM Convention.
2
EU Member Countries should take into account the Directive 2011/92/EU of the European Parliament and of the Council of 13 December
2011 on the assessment of the effects of certain public and private projects on the environment. Where applicable, the EU Habitat Directive
(92/43/EEC) may require an appropriate assessment and the EU-Landfill (99/31/EC) and Water Framework Directives (2000/60/EC) may
have implications for dredging and deposit operations. Additionally Directive 2008/56/EC Establishing a Framework for Community Action in
the Field of Marine Environmental Policy (Marine Strategy Framework Directive) specifies the deposit of dredged material as a possible
pressure with regard to physical loss or damage which needs to be considered when assessing the status of the marine environment.
Page
4
of 39
iterative manner (revisiting steps in the processes as needed) ensuring that all steps receive
consideration, including consideration of BAT and BEP, before a decision is made to issue or decline a
permit. The following sections of this document describe the steps and activities relevant to the
Guidelines.
3. REQUIREMENTS OF THE 1992 HELSINKI CONVENTION
3.1 Within the framework of the Convention for the Protection of the Marine Environment of the Baltic Sea
(hereinafter called the 1992 Helsinki Convention), dredged materials may, in accordance with Article 11
of the Convention and Annex V, be permitted to be dumped at sea.
3.2 With regard to the dumping of dredged material at sea, Article 11 (2) of the Helsinki Convention requires
Contracting Parties to ensure that no such materials are dumped without permission issued by their
appropriate competent authorities.
3.3 Regulation 1 a) of Annex V of the Convention requires that dumping of dredged material containing
harmful substances indicated in annex I of the Convention is only permitted according to these guidelines
adopted by the Commission.
3.4 Regulation 2 (3) of Annex V requires Contracting Parties to report to the Commission on the nature and
quantities of dumped material in accordance with Regulation 2 (1c) of this Annex. To this end, HELCOM
has agreed on reporting formats for the submission of data on wastes dumped at sea.
3.5 Furthermore, according to the HELCOM Recommendation 20/4 the Contracting Parties are
recommended to report on organic tin concentrations in the marine environment in areas where its
compounds may be entering to marine environment.
4. PRELIMINARY CONSIDERATIONS FOR DREDGED MATERIAL MANAGEMENT
4.1 Before beginning a full assessment of the material and the deposit options the first considerations should
be the scale and need for the dredging project. In the event of a subsequent full assessment indicating no
acceptable options for deposit it will be necessary to re-address this question in a broader context.
4.2 Reducing adverse effects on the marine environment can be accomplished through the following three
activities:
.1 Controlling and reducing sources of contamination;
.2 Maximizing the use of dredged material for beneficial purposes;
.3 Minimizing the volumes of sediment that must be dredged by using improved Best Environmental
Practices (BEP), as discussed in Technical Annex III
4.3 Contamination of the aquatic environment, both as a consequence of historical and present day inputs,
presents a problem for the management of freshwater, estuarine, and marine sediments. High priority
should be given to the identification of sources, as well as the reduction and prevention of further
contamination of sediments from both point and diffuse sources. Successful implementation of
prevention strategies will require collaboration among competent authorities with responsibility for the
control of contaminant sources.
It would be recommendable to include the following sources of contamination, e.g.:
industrial and domestic discharges;
storm water;
surface runoff from agricultural areas;
sewage and waste-water treatment effluents;
transport from upstream contaminated sediments.
accidental pollution
4.4 In developing and implementing a source control strategy, competent authorities should take into
account:
Page
5
of 39
.1 the risks posed by contaminants and the relative contributions of the individual sources to these
risks;
.2 existing source control programmes and other regulations or legal requirements;
.3 best available techniques (BAT) and BEP as defined in Annex II of the 1992 Helsinki Convention, inter
alia, as regards the technical and economic feasibility;
.4 evaluations of the performance or effectiveness of measures taken
.5 consequences of not implementing source control.
4.5 In cases where control measures are not fully effective in reducing contamination and high levels of
contamination persist then specific dredged material management options may be required, for example
confined deposit facilities or treatment methods.
4.6 Sediment is a valuable natural resource. Beneficial uses of dredged material (which are described further
in Section 7) should be pursued to the maximum extent practicable. Beneficial use of sediments includes
retaining sediments that meet national assessment criteria within freshwater, estuarine, and marine
systems.
4.7 There is a need to minimize the release of contaminants to the environment while maximizing the re-
use of sediment for beneficial purposes. Progress toward more sustainable practice in respect to
sediment management (including dredged material management) can be seen in initiatives being
undertaken by Contracting Parties, such as Building with Nature and Observers to the Convention, such
as Working with Nature (PIANC 2011).
4.8 In addition, attention needs to be given to ensuring that the quantities of material needing to be dredged
and deposited of at sea are minimised as far as is practicable. Application of BEP (technical annex III) to
dredging operations minimises the quantity of material that must be dredged and deposited of at sea
thereby reducing the environmental impact of dredging activities (e.g., PIANC 2009 and CEDA 2010).
5. DREDGED MATERIAL SAMPLING
Sampling for the purpose of issuing a depositing permit
5.1 Dredged material that is not exempted under paragraph 6.3 will require analysis and testing (cf. Technical
Annex I) to obtain sufficient information for permitting purposes. Judgement and knowledge of local
conditions will be essential when deciding what information is relevant to any particular operation.
5.2 A survey of the area to be dredged should be carried out. The distribution and depth of sampling should
reflect the size and depth of the area to be dredged, the amount to be dredged and the expected
variability in the horizontal and vertical distribution of contaminants. Core samples should be taken where
the depth of dredging and expected vertical distribution of contaminants suggest that this is warranted.
In other circumstances, grab sampling may be sufficient. Pollutant load calculations should take into
consideration sampling depth and the depth of dredging as well as appropriate weighting of heavily
polluted spots. Sampling from dredgers or barges is not advisable for permitting purposes.
5.3 The number of sample stations can be determined on the basis of the amount of dredged material or
the area to be dredged. If the thickness of the sediment to be dredged on average is small (e.g. up to 1
meter depth) area-focused approach is recommended to determine the number of sampling stations.
Otherwise if the thickness of the sediment to be dredged on average exceeds 1 meter then amount
approach is considered to determine the numbers of sampling stations.
The following tables give an indication of the minimum number of separate sampling stations depending
on which approach is taken into account to obtain representative results:
Page
6
of 39
Amount approach
Amount dredged (m
3
) Number of Stations
Up to 25 000 3
25 000 - 100 000 4 6
100 000 - 500 000 7 15
500 000 - 2 000 000 16 30
>2 000 000 extra 10 per million m
3
Area approach
Dredged area (m
2
) Number of Stations
<10 000 1 - 3
10 000 50 000 4 8
50 000 100 000 9 10
>100 000 extra 5 per 100 000 m
2
The number of sample stations should take account of the exchange characteristics of the area; more
samples may be required in enclosed and semi-enclosed areas and less in open areas. Contracting Parties
are encouraged to use the Guidelines for the Sampling and Analysis of Dredged Material Intended for
Disposal at Sea (IMO, 2005).
5.4 Normally, the samples from each sampling station and different depths in the sediment should be
analysed separately. However, if the sediment is clearly homogenous with respect to sediment texture, it
may be possible to analyse composite samples from two or more adjacent sampling stations at a time,
providing there are no distinctly different contaminant concentrations in different sub samples and care
is taken to ensure that the results allow derivation of valid mean contaminant values. The original
individual samples should, however, be retained until the permitting procedure has been completed, in
case further analyses are necessary.
Frequency of sampling
5.5 If the results of the analyses indicate that the material is essentially ‘clean (i.e. below the lower action
level (paragraph 6.13), sampling in the same area need not be repeated more frequently than once every
3 years, provided that there is no indication that the quality of the material has deteriorated.
5.6 It may be possible, following assessment of the results of an initial survey, to reduce either the number
of sampling stations or the number of determinants and still provide sufficient information for permitting
purposes. If a reduced sampling programme does not confirm the earlier analyses, the full survey should
be repeated. If the list of determinants is reduced, further analysis of the complete list of determinants
is advisable every 5 years.
5.7 In areas where there is a tendency for sediments to exhibit high levels of contamination, analysis of all
the relevant determinants should be frequent and linked to the permit renewal procedure.
6. DREDGED MATERIAL CHARACTERISATION
6.1 Characterisation should take into consideration physical and chemical characteristics, while biological
characteristics are optional. A list of the data to be collected and analysed during the characterization
process should be developed on a project-specific basis. This data should be sufficient to describe and
Page
7
of 39
assess possible impacts as a basis for management decisions (e.g. PIANC 1996; 1998a and b). Guidance
on the selection of determinants and methods of contaminant analysis, together with procedures to be
used for normalisation and quality assurance purposes, will be found in the Technical Annexes. It is
envisaged that developments in biological testing techniques might eventually provide sufficient
information to assess the potential impact of the contaminants in the material, so that less reliance
would need to be placed on chemical testing.
6.2 If dredged material is so poorly characterised that proper assessment cannot be made of its potential
impacts on human health and the environment, it shall not be deposited at sea unless there is an
overriding public interest e.g. in relation to safety and civil protection.
Exemptions from detailed characterisation
6.3 Dredged material may be exempted from the testing referred to in paragraphs 6.5 to 6.7 of these
Guidelines (but note that the information listed in paragraph 6.4 below will still be required) if any of the
criteria below are met:
a. it is composed of previously undisturbed geological material; or
b. it is composed almost exclusively of sand, gravel or rock; or
c. in the absence of appreciable past and present pollution sources and when the quantity of dredged
material from operations does not exceed 10.000 tonnes per year (use conversion factors between
cubic meters and tonnes (dry weight) from the HELCOM Reporting Format for Management of
Dredged Material at Sea (Attachment 1)).
In relation to 6.3b and 6.3c the exemption from testing should be supported by local information so as to
provide reasonable assurance that the dredged material has not been contaminated.
Dredged material that does not meet at least one of these requirements will need further stepwise
characterisation to assess its potential impact (i.e. see paragraphs 6.4-6.11).
Physical characterisation
6.4 The following information is required:
a. the amount of material;
b. anticipated or actual deposit rate of material at the deposit site;
c. sediment characteristics by grain size analysis (laser or sieving methods) or exceptionally on the
basis of visual determination (i.e. clay/silt/sand/gravel/boulder).
Evaluation of the physical characteristics of sediments for deposit is necessary to determine potential impacts
and the need for subsequent chemical and/or biological testing (cf. Technical Annex I for further guidance).
Conversion factors for cubic meters of dredged material to metric tonnes are given in the HELCOM Reporting
Format for Management of Dredged Material at Sea (Attachment 1).
Chemical characterisation
6.5 Sufficient information for chemical characterisation may be available from existing sources, i.a. for similar
material in the vicinity. In such cases new measurements of the potential impact may not be required,
provided that this information is still reliable and has been obtained within the last 5 years. Details of the
substances to be determined are listed in Technical Annex I.
Considerations for additional chemical characterisation of dredged material are as follows:
a. major geochemical characteristics of the sediment including redox status;
b. potential routes by which contaminants could reasonably have been introduced to the sediments;
for example, tin compounds reaching marine environment from previous use of antifouling paints
and others can be expected in harbours and marinas
c. industrial and municipal waste discharges (past and present);
Page
8
of 39
d. probability of contamination from agricultural and urban surface runoff;
e. spills of contaminants in the area to be dredged;
f. source and prior use of dredged materials (e.g., beach nourishment); and
g. natural deposits of minerals and other natural substances.
6.6 Further information may also be useful in interpreting the results of chemical testing (see Technical
Annex I).
Biological characterisation
6.7 If the potential impacts of the dredged material to be deposited cannot be adequately assessed on the
basis of the chemical and physical characterisation and available biological information, biological testing
may be conducted. Further detailed guidance on biological testing is provided in Technical Annex I.
6.8 Biological tests should incorporate species that are considered appropriately sensitive and
representative and should determine, where appropriate.
a. acute toxicity;
b. chronic toxicity;
c. the potential for bioaccumulation; and
d. the potential for tainting.
6.9 Assessment of habitats communities and populations may be conducted in parallel with chemical and
physical characterisation, e.g. triad approach. It is important to ascertain whether adequate scientific
information exists on the characteristics and composition of the material to be deposited and on the
potential impacts on marine life and human health. In this context, it is important to consider information
about species known to occur in the area of the deposit site and the effects of the material to be deposited
and of its constituents on organisms.
Action List
6.10 The Action List is used as a screening mechanism for assessing properties and constituents of
dredged material with a set of criteria for specific substances e.g. toxicity, persistence and bio-
accumulation It should be used for dredged material management options (cf. Section 7), including the
identification and development of source control measures as described in Section 4. The criteria should
reflect experience gained relating to the potential effects on human health or the marine environment.
6.11 Action List levels should be developed on a national or regional basis and might be set on the
basis of concentration limits, biological responses, environmental quality standards, flux considerations
or other reference values. They should be derived from studies of sediments that have similar
geochemical properties to those from the ones to be dredged and/or to those of the receiving system.
Thus, depending upon natural variation in sediment geochemistry, it may be necessary to develop
individual sets of criteria for each area in which dredging or deposit is conducted. With a view to
evaluating the possibilities for harmonising or consolidating the criteria referred to above, Contracting
Parties are requested to inform the Helsinki Commission of the criteria adopted, as well as the scientific
basis for the development and refinement of these criteria.
6.12 An Action List should specify an upper level and may also specify a lower level giving these
possible actions:
a. material, which contains specified contaminants or which causes biological responses, in excess of
the relevant upper levels should generally be considered unsuitable for deposit at sea
b. material of intermediate quality which contains contaminants below the upper level but exceeding
the lower level, requires more detailed assessment before suitability for deposit at sea can be
determined; and
Page
9
of 39
c. material, which contains contaminants, below the lower levels should generally be considered of
little environmental concern for deposit at sea.
6.13 Action levels need to be established at least for determinants on the Primary list in Technical
Annex I.
6.14 If, as an option of least detriment, dredged material is deposited at sea when one or more
criteria exceed the upper level, a Contracting Party should:
a. where appropriate, identify and develop source control measures with a view to meeting the criteria
(see paragraphs 4.3 - 4.4 above); and
b. utilise deposit management techniques, including the confined disposal or treatment methods, to
mitigate the impact of the deposit operation on the marine environment (see paragraphs 7.3 - 7.5
below); and
c. report the fact to the Secretariat, including the reason for permitting the deposit, in accordance
with the reporting form for the annual reporting.
7. DREDGED MATERIAL MANAGEMENT OPTIONS
7.1 Generally it is the preferred option to keep the sediment in the aquatic, estuarine, or marine system,
however the results of the physical/chemical/biological characterisation will determine the dredged
material management options. Examples of management options include beneficial use, unrestricted,
open-water deposit, confined aquatic deposit or confined deposit facilities. In some cases the best option
may be to leave the material in-situ. Additional information about beneficial uses of dredged material,
including case studies, can be found at the Central Dredging Associations website. PIANC (2009) provides
technical information on the assessment of options for beneficial use and recommendations on how to
overcome constraints based on lessons learned from numerous cases studies in different situations in
various countries.
Options for material assessed to be uncontaminated
3
7.2 There is a wide variety of beneficial use depending on the physical and chemical characteristics of the
material. Generally, a characterisation carried out in accordance with these guidelines will be sufficient
to match a material to possible uses such as:
.1 Sustainable Placement by retaining sediment within the natural sediment system to support
sediment-based habitats, shorelines, and infrastructure.
.2 Habitat Restoration and Development using direct placement of dredged material for enhancement
or restoration of natural habitat associated with wetlands, other near-shore habitats, coastal
features, offshore reefs, fisheries enhancement, etc.
.3 Beach Nourishment using dredged material (primarily sandy material) to restore and maintain
beaches.
.4 Shoreline Stabilization and Protection through the placement of dredged material with the intent
of maintaining or creating erosion protection, dike field maintenance, berm or levee construction,
and erosion control.
.5 Engineering uses (e.g. as capping material or for land reclamation).
Options for material assessed to be contaminated
7.3 Where the characteristics of' the dredged material are such that normal sea deposit would not meet the
requirements of the 1992 Helsinki Convention, treatment or other management options should be
considered. These options can be used to reduce or control impacts to a level that will not constitute an
unacceptable risk to human health, or harm living resources, damage amenities or interfere with
legitimate uses of the sea.
3
according to national assessment criteria
Page
10
of 39
7.4 Treatment, such as separation of contaminated fractions, may make the material suitable for a beneficial
use and should be considered before opting for sea deposit. Deposit management techniques to reduce
or control impacts may include e.g. deposit on or burial in the sea floor followed by clean sediment
capping, or methods of containing dredged material in a stable manner. Advice on dealing with
contaminated dredged material is available from PIANC (see references).
7.5 The practical availability of other means than deposit at sea should be considered in the light of a
comparative risk assessment involving both deposit and the alternatives.
8. SITE SELECTION
8.1 The selection of a site for sea deposit involves considerations of an environmental nature and also
economic and operational feasibility. Site selection should try to ensure that the deposit of dredged
material does not interfere with, or devalue, legitimate commercial and economic uses of the marine
environment nor produce undesirable effects on vulnerable marine ecosystems or species and habitats
on the HELCOM Red List of Baltic Sea species in danger of becoming extinct (BSEP140) and the Red List of
Baltic Sea underwater biotopes, habitats and biotope complexes (BSEP138)
8.2 For the evaluation of a sea deposit site information should be obtained and assessed on the following,
as appropriate:
a. the physical, chemical and biological characteristics of the seabed (e.g., topography, sediment
dynamics and transport, redox status, benthic biota);
b. the physical, chemical and biological characteristics of the water column (e.g., hydrodynamics,
dissolved oxygen, pelagic species); and
c. proximity to:
(i). areas of natural beauty or significant cultural or historical importance;.
(ii). areas of specific scientific or biological importance;
(iii). recreational areas;
(iv). subsistence, commercial and sport fishing areas;
(v). spawning, recruitment and nursery areas;
(vi). migration routes of marine organisms;
(vii). shipping lanes;
(viii). military exercise zones;
(ix). past munitions disposal sites;
(x). engineering uses of the sea such as undersea cables, pipelines, etc.
(xi). areas of mineral resources (e.g. sand and gravel extraction areas)
d. the capacity of the site should be assessed, taking into account:
the anticipated loading rates per day, week, month, or year;
the degree to which the site is dispersive;
the allowable reduction in water depth over the site because of mounding of material.
Such information can be obtained from existing sources, complemented by field work where
necessary.
8.3 The information on the characteristics of the sea deposit site referred to above is required to determine
the probable fate and effects of the deposited material. The physical conditions in the vicinity of the sea
deposit site will determine the transport and fate of the dredged material. The physico-chemical
conditions can be used to assess the mobility and bioavailability of the chemical constituents of the
material. The nature and distribution of the biological community and the proximity of the site of sea
Page
11
of 39
deposit to marine resources and amenities will, in turn, define the nature of the effects that are to be
expected. Careful evaluation will allow determination of environmental processes that may dominate the
transport of material away from the sea deposit site. The influence of these processes may be reduced
through the imposition of permit conditions.
8.4 In some cases, depositing of dredged material can augment existing effects attributable to inputs of
contaminants to coastal areas through land runoff and discharge, from the atmosphere, resource
exploitation and maritime transport. These existing stresses on biological communities should be
considered as part of the assessment of potential impacts caused by the deposit operation. The proposed
method of depositing and potential future uses of resources and amenities in the marine receiving area
should also be taken into account.
8.5 Information from baseline and monitoring studies at already established deposit sites will be important
in the evaluation of any new depositing activity at the same site or nearby.
8.6 For contaminated material the use of open-sea sites at distant off-shore locations is seldom an
environmentally desirable solution to the prevention of marine pollution by contaminated dredged
material.
8.7 The dredged material which is acceptable for sea deposit and the sediments at the chosen site, or in case
of a dispersive deposit site for the sediments of the receiving area, should be similar as far as possible.
9. ASSESSMENT OF POTENTIAL EFFECTS
Deposit sites
9.1 Assessment of potential effects should lead to a concise statement of the expected consequences of the
deposit option (i.e., the Impact Hypothesis). Its purpose is to provide a basis for deciding whether to
approve or reject the proposed deposit option and for defining environmental monitoring requirements.
9.2 This assessment should integrate information on the characteristics of the dredged material and the
proposed deposit site conditions. It should comprise a summary of the potential effects on human health,
living resources, amenities and other legitimate uses of the sea and should define the nature, temporal
and spatial scales and duration of expected impacts based on reasonably pessimistic assumptions.
9.3 In order to develop the hypothesis, it may be necessary to conduct a baseline survey which describes not
only the environmental characteristics, but also the variability of the environment. It may be helpful to
develop sediment transport, hydrodynamic and other models, to determine possible effects of deposit.
9.4 For a retentive site, where the material deposited will remain within the vicinity of the site, the assessment
should delineate the area that will be substantially altered by the presence of the deposited material and
what the severity of these alterations might be. At the extreme, this may include an assumption that the
immediate receiving area is entirely smothered. In such a case, the likely timescale of recovery or re-
colonisation should be projected after deposit operations have been completed as well as the likelihood
that re-colonisation will be similar to, or different from, the existing benthic community structure. The
assessment should specify the likelihood and scale of residual impacts outside the primary zone.
9.5 In the case of a dispersive site, the assessment should include a definition of the area likely to be altered
in the shorter term by the proposed deposit operation (i.e., the near-field) and the severity of associated
changes in that immediate receiving environment. It should also specify the likely extent of long-term
transport of material from this area and what this flux represents in relation to existing transport fluxes
in the area, thereby permitting a statement regarding the likely scale and severity of effects in the long-
term and far-field.
9.6 For the Contracting Parties that are also EU Member States, the Directive 2011/92/EU of the European
Parliament and of the Council of 13 December 2011 on the assessment of the effects of certain public
and private projects on the environment should be taken into account when assessing potential impacts
of dredged material deposit. Where applicable, the EU-Habitats Directive (92/43/EEC) may require an
appropriate assessment and the EU-Landfill (99/31/EC) and Water Framework Directives (2000/60/EC)
Page
12
of 39
Establishing a Framework for Community Action in the Field of Marine Environmental Policy (Marine
Strategy Framework Directive) specifies the deposit of dredged material as a possible pressure with
regard to physical loss or damage which needs to be considered when assessing the status of the marine
environment.
Nature of the impact
9.7 All dredged materials have a significant physical impact at the point of deposit. This impact includes
covering of the seabed and local increases in suspended solids levels. Physical impact may also result from
the subsequent transport, particularly of the finer fractions, by wave and tidal action and residual current
movements.
9.8 Biological consequences of these physical impacts include smothering of benthic organisms in the deposit
area and potentially in the surrounding area. In specific circumstances, the physical impacts can also
interfere with sensitive life stages and/or the migration of fish (e.g. egg,larvae stages and the impact of
high levels of turbidity on salmonids in estuarine areas) or crustaceans (e.g. if deposition occurs in the
coastal migration path of crabs).
9.9 The toxicological and bioaccumulation effects of' dredged material constituents should be assessed.
Deposit of sediments with low levels of contamination is not devoid of environmental risk and requires
consideration of the fate and effects of dredged material and its constituents. Substances in dredged
material may undergo physical, chemical and biochemical changes when entering the marine
environment and these changes should be considered in the light of the eventual fate and potential
effects of the material. It should also be taken into account that deposit at sea of certain substances may
disrupt the sensory capabilities of the fish and may mask natural characteristics of sea water or tributary
streams, thus confusing migratory species which e.g. fail to find spawning grounds or food.
9.10 In relatively enclosed waters, such as some estuarine, archipelagic and fjordic situations,
sediments with a high chemical or biological oxygen demand (e.g. organic carbon-rich) could adversely
affect the oxygen regime of the receiving environment while sediments with high levels of nutrients
could significantly affect the nutrient flux.
9.11 An important consequence of the physical presence of dredged material deposit activities is
interference with fishery activities and in some instances with navigation and recreation. These problems
can be aggravated if the sediment characteristics of the dredged material are very dissimilar to that of
the ambient sediment or if the dredged material is contaminated with bulky harbour debris such as
wooden beams, scrap metal, pieces of cable etc.
9.12 Particular attention should be given to dredged material containing significant amounts of oil
or other substances that have a tendency to float following re-suspension in the water column. Such
materials should not be deposited in a manner or at a location which may lead to interference with
protected species and habitats (cf. 8.1), fishing, shipping, amenities or other beneficial uses of the marine
environment.
10. PERMIT OR REGULATION BY OTHER MEANS
10.1 If sea deposit is the selected option, then a permit or regulation by other means (which is in
compliance with these guidelines) authorizing sea deposit must be issued in advance. In granting a permit,
the immediate impact of dredged material occurring within the boundaries of the deposit site such as
alterations to the local, physical, chemical and biological environment is accepted by the permitting or
supervising authority, provided that adverse effects on ecosystems components and ecosystem
functions are avoided. Notwithstanding these consequences, the conditions under which a permit for sea
deposit is issued should be such that environmental change beyond the boundaries of the deposit site are
as far below the limits of allowable environmental change as practicable. The deposit operation should
be permitted subject to conditions which further ensure that environmental disturbance and detriment
are minimised and benefits maximised.
Page
13
of 39
10.2 The permit is an important tool for managing sea deposit of dredged material and will contain
the terms and conditions under which sea deposit may take place as well as provide a framework for
assessing and ensuring compliance.
10.3 Permit conditions should be drafted in plain and unambiguous language and will be designed
to ensure that:
a. only those materials which have been characterised or considered exempted from detailed
characterisation according to paragraph 6.3 and found acceptable for sea deposit, based on
the impact assessment, are deposited;
b. solid waste
4
contained within the dredged material should be separated and managed on
land;
c. the material, up to licensed quantity, is deposited at the selected deposit site;
d. any necessary deposit management techniques identified during the impact analysis are
carried out; and
e. any monitoring requirements are fulfilled and the results reported to the permitting or
supervising authority.
10.4 A permit to deposit contaminated dredged material exceeding national criteria should
generally be considered unsuitable / shall be be refused, if the permitting authority determines that
appropriate opportunities exist to reuse, recycle or treat the material without undue risks to human
health or the environment or disproportionate costs.
11. MANAGEMENT OF THE DEPOSIT OPERATION
11.1 This section deals with management techniques to minimise the physical effects of dredged
material deposit. The key to management lies in careful site selection and an assessment of the potential
for conflict with other interests and activities. In addition, appropriate methods of dredging and of deposit
should be chosen in order to minimise the environmental effects. Guidance is given in Technical Annex III.
11.2 Where appropriate, deposit vessels should be equipped with accurate positioning systems
which shall be switched on recording mode during deposit operations and the activity of the vessels may
be reported to the permitting and supervising authority. Deposit vessels and operations should be
inspected regularly to ensure that the conditions of the deposit permit are being complied with and that
the crew are aware of their responsibilities under the permit. Ships' records and automatic monitoring
and display devices (e.g. black-boxes), where these have been fitted, should be inspected to ensure that
deposit is taking place at the specified deposit site.
11.3 In most cases, blanketing of a comparatively small area of seabed is considered to be an
acceptable environmental consequence of deposit. To avoid excessive degradation of the seabed as a
whole, the number of sites should be limited as far as possible and each site should be used to the
maximum extent that will not interfere with navigation or any other legitimate use of the sea.
11.4 Effects can be minimised by ensuring that, as far as possible, the dredged material and the
sediments in the receiving area are similar. Locally, impacts may also be reduced if the deposition area
is subject to natural physical disturbance. In areas where natural dispersion is low or unlikely to be
significant and where reasonably clean, finer-grained dredged material is concerned, it may be
appropriate to use a deliberately dispersive deposit strategy to prevent or reduce blanketing, particularly
of a smaller site (see also 9.5).
11.5 The rate of deposition of dredged material can be an important consideration since it will often
have a strong influence on the impacts at the deposit site. It may therefore need to be controlled to
ensure that the environmental management objectives for the site are not exceeded.
4
as defined in the glossary
Page
14
of 39
11.6 Engineering controls, such as method of dredging and deposit, remediation of contaminated
materials, infilling of depressions, deliberate capping or other contained methods of deposit of dredged
material deposits may be appropriate in certain circumstances to avoid interference with fishing or other
legitimate activities.
11.7 Operational controls can include temporal restrictions on depositing activities such as tidal
and/or seasonal restrictions to prevent interference with e.g. nature protection, anthropogenic uses,
migration, spawning or seasonal fishing activity.
12. MONITORING
12.1 Monitoring in relation to deposit of dredged material is defined as measurements of
compliance with permit requirements and of the condition and changes in condition of the receiving area
to assess the Impact Hypothesis upon which the issue of a deposit permit was approved.
12.2 The effects of dredged material deposit are likely to be similar in many areas, and it would be
very difficult to justify (on scientific or economic grounds) monitoring all sites, particularly those receiving
small quantities of dredged material. It is therefore more appropriate, and cost effective, to concentrate
on detailed investigations at a few carefully chosen sites (e.g. those subject to large inputs of dredged
material) to obtain a better understanding of processes and effects.
12.3 It may usually be assumed that suitable specifications of existing (pre-deposit) conditions in the
receiving area are already contained in the application for deposit
12.4 The Impact Hypothesis forms the basis for defining the monitoring programme. The
measurement programme should be designed to ascertain that changes in the receiving environment are
within those predicted. In designing a monitoring programme the following questions must be answered:
a.
b.
what testable hypotheses can be derived from the Impact Hypothesis?
what measurements (e.g. type, location, frequency, performance requirements) are required to
test these hypotheses?
c.
what should be the temporal and spatial scale of measurements?
d.
how should the data be managed and interpreted?
12.5
The permitting or supervising authority is encouraged to take account of relevant research
information in the design and modification of monitoring programmes. Measurements should be
designed to determine two things:
a. whether the zone of impact differs from that projected; and
b. whether the extent of change protected outside the zone of impact is within the scale predicted.
The first of these questions can be answered by designing a sequence of measurements in space and
time that circumscribe the projected zone of impact to ensure that the projected spatial scale of change
is not exceeded. The second question can be answered by the acquisition of measurements that provide
information on the extent of change that occurs outside the zone of impact after the deposit operation.
Frequently, this latter suite of measurements will only be able to be based on a null hypothesis - that no
significant change can be detected.
Feedback
12.6 Information gained from field monitoring, (or other related research studies) can be used to:
a. modify or terminate the field monitoring programme;
b. modify or revoke the permit; and
c. refine the basis on which applications to deposit dredged material at sea are assessed.
Page
15
of 39
12.7 Concise statements of monitoring activities should be prepared. Reports should detail the
measurements made, results obtained and how these data relate to the monitoring objectives. The
frequency of reporting will depend upon the scale of deposit activity and the intensity of monitoring.
13. REPORTING
13.1 According to 1992 Helsinki Convention Annex V Regulation 2 and Article 11 item 5 the
Contracting Parties should report on nature and quantities of material that has been deposited in the
Baltic Sea Area. This should be done according to the HELCOM Reporting Format for Management of
Dredged Material at Sea (Attachment 1).
13.2 Contracting Parties should also inform the Secretariat of their monitoring activities and submit
reports when they are available.
Figure 1: Steps to be considered in assessing permits application for sea deposit
Page
16
of 39
13.3 According to the decision of (HELCOM 41-2020), the HELCOM Secretariat annually reports to the London
Convention and its 1996 Protocol on behalf of HELCOM Contracting Parties. The Consolidated report is to
be prepared utilizing the data on handling of dredged material at sea that are annually reported by the
Contracting Parties, pursuant to HELCOM Recommendation 36-2 REV. The format and technical
requirements for the consolidated reporting were agreed between the Secretariats of the London
Convention and the Helsinki Convention taking into account the availability of relevant data in the
Contracting Parties to the Helsinki Convention. The annual consolidated report to LC/LP is to be prepared in
the format given in the Attachment 2 to this Guideline.
- The report consists of two excel sheets: “summary” and “details of sites”. In addition, the report
includes a word file with definitions used in the HELCOM reporting on handling of dredged material at
sea.
- The “summary sheet” is comprised of a country wise summary of activities on the reporting year. It
includes information on the number of activities and the amount material deposited, both separated
between capital and maintenance dredging. In addition, it includes a map on the distribution of
activities around the Baltic Sea.
- The “details of sites” sheet is comprised of information on individual depositing activities, including
deposit site code, location of site (coordinates of the site), sub basin and amount material deposited.
Information on the beneficial use is also provided and the last two columns includes the potential
amount and purpose of beneficial use.
The procedure and timeframe of the reporting include the following steps:
- An overview of the data reported in accordance with the Annex 1 to this Guideline is to be presented
to the relevant HELCOM working group at the first convenience after the reporting deadline for taking
necessary actions to accomplish the reporting.
- The reported data will be processed by the Secretariat and compiled into the unified geo-database by
1 December of the same year including all needed clarifications with national data reporters.
- The compiled national datasets will be available for national data reporters after 1 December in
Shapefile format. National experts will be invited to verify and approve the datasets in two months’
time by 1 February of the following year.
- After expert’s approval HELCOM Secretariat will compile the consolidated report from the verified
data by 1 March and submit it LC/LP after approval by relevant HELCOM working group.
Page
17
of 39
14. REFERENCES
Background information and supplementary literature to the HELCOM Guidelines for the Management of
Dredged Material at Sea
Application of ecosystem principles for the location and management of offshore dumping sites in the SE Baltic
Region (ECODUMP Project)
Clarifications regarding the relationship between the existing national interpretations in the application of the
Waste Framework Directive to dredged materials and the dredged material management guidelines, HELCOM
LAND-MONAS EWS DREDGE 2-2014 (document 4-1, Annex II)
EPA/CE, 1992. Evaluating Environmental Effects of Dredged Material Management Alternatives - A Technical
Framework, EPA 842-B-92-008.
IMO 2005. Sampling of Dredged Material guidelines for the sampling and analysis of dredged material intended
for disposal at sea. IMO publication 1537E.
International Association of Dredging Companies (IADC)/Central Dredging Association (CEDA), 1997.
Environmental Aspects of Dredging, Guide 2a: Conventions, Codes and Conditions: Marine Disposal.
International Association of Dredging Companies (IADC)/Central Dredging Association (CEDA), 1997.
Environmental Aspects of Dredging. Guide 3 (Investigation, Interpretation and Impact). ISBN 90-75254-08-3.
International Association of Dredging Companies (IADC)/Central Dredging Association (CEDA), 1998.
Environmental Aspects of Dredging, Guide 4: Machines, Methods and Mitigation.
International Association of Dredging Companies (IADC)/Central Dredging Association (CEDA), 1999.
Environmental Aspects of Dredging, Guide 5: Reuse, Recycle or Relocate.
PIANC, 1992. Beneficial Uses of Dredged Material: A Practical Guide, Report of Working Group No. 19.
PIANC, 1996. Handling and Treatment of Contaminated Dredged Material from Ports and Inland Waterways,
Report of Working Group No. 17 of the Permanent Technical Committee 1 -Supplement to PIANC Bulletin No. 89.
PIANC, 1997. Dredged Material Management Guide. Special Report of the Permanent Environmental Commission
Supplement to Bulletin no.96.
PIANC, 1998. Handling and Treatment of Contaminated Dredged material from Ports and Inland Waterways, Vol.
2., Report of Working Group No. 17 of the Permanent Technical Committee 1.
PIANC, 1999. Management of Aquatic Disposal of Dredged Material. Report of ENVICOM Working Group 1 of the
Permanent Environmental Commission.
Sustainable Management of Contaminated Sediments (SMOCS Project); Guidelines for applying sustainability
approach for management of contaminated sediments in dredging projects.
Page
18
of 39
Glossary and Acronyms
These terms are defined for the purpose of these guidelines
Annex I
Action Levels
Guidance values used to trigger action
anoxic
Without oxygen.
anthropogenic
Originating from the activity of humans.
benthic
Of, relating to, or occurring at the bottom of a body of water.
Best Available
Techniques (BAT)
The latest stage of development (state of the art) of processes, of facilities or of
methods of operation, which indicate the practical suitability of a particular
measure for limiting discharges, emissions and waste. (Regulation 2, Annex II of
the Helsinki Convention 1992)
Best Environmental
Practice (BEP)
The application of the most appropriate combination of environmental control
measures and strategies. (Regulation 3, Annex II of the Helsinki Convention 1992)
bioaccumulation
Accumulation of environmental contaminants in living tissue.
bioassay
Tests in which organisms are exposed to dredged materials to determine their
effects or toxicity.
biological testing
Testing via bioassays.
biota
Living organisms.
Building with Nature
New approach to maritime
infrastructure
projects using the dynamics of the natural system
as a starting point.
CEDA
Central Dredging Association, one of the three autonomous sister organizations,
along with WEDA and EADA, that constitute WODA.
clay
Sedimentary mineral particles 0.2 to 2.0 µm in size, usually with a negative charge
(anion); the size and charge have profound implications for sediment chemistry
and other physical interactions.
Contaminated dredged
material
Dredged material not meeting national assessment criteria (e.g. exceeding upper
action levels).
confined disposal
Deposit in a structure planned and designed to contain dredged material and
safely contain any released contaminants, preventing their re-entry into the
aquatic environment.
deposit
Any deposit into the maritime area of dredged materials, independently of
whether it is considered as dumping or placement
dredged material
Material arising from dredging operations.
dredged material
management
Is an overarching term describing a variety of handling methods of dredged
materials including, inter alia: dumping (deliberate disposal), re-use, beneficial
use, re-location, placement and treatment.
Page
19
of 39
dumping
any deliberate disposal at sea or into the seabed of dredged material; subject to a
prior special permit issued by the appropriate national authority in accordance
with the provisions of Annex V of the 1992 Helsinki Convention (Article 2 (4ai), 11
(2))
eco-toxicological
testing
Biological testing via bioassays.
gravel
Unconsolidated rock fragment > 2mm to < 63mm
fractions
Categories of sediments using grain size.
persistence
feature of organic compounds to resist to environmental degradation through
chemical, biological, and photolytic processes
(i) Evidence that the half-life of the chemical in water is greater than two months,
or that its half-life in soil is greater than six months, or that its half-life in sediment
is greater than six months; or
(ii) Evidence that the chemical is otherwise sufficiently persistent to justify its
consideration within the scope of this Convention (Stockholm POPs Convention);
permitting authority
The official department or agency that has the legal authority to permit or refuse
deposit in the marine environment and to prosecute violations of deposit
regulations.
PIANC
The International Navigation Association.
placement
placement of matter for a purpose other than the mere disposal thereof,
provided that such placement is not contrary to the aims of the present
Convention (Article 2 (4bii) of the 1992 Helsinki Convention)
practicable
Idea that a project, or scheme that can be realized, with the available resources
and within the given constraints of cost and time.
sand
Mineral particles > 63 µm and < 2 mm in size.
sediment
Naturally occurring material that is produced through the processes of
weathering and erosion of rocks, and is subsequently transported by the action of
fluids such as wind, water, or ice, and/or by the force of gravity acting on the
particle itself.
sidecast dredging
most common currently applied method to outfall construction involving
dredging or excavation of a trench, and placing of excavated material on the
seabed to one or both sides of the trench
silt
Mineral particles between 2.0 µm and 63 µm in size;
solid waste
Any persistent, manufactured or processed solid material or items discarded,
deposited of or abandoned in the marine and coastal environment
toxic
Has lethal or debilitating effects when ingested or contacted externally, such as
exposure to gill membranes during respiration or to skin.
treatment
The processing of (contaminated) dredged material to reduce its quantity or to
reduce the contamination.
Page
20
of 39
Analytical Requirements for Dredged Material Assessment
Technical Annex I
1. This Technical Annex covers the analytical requirements necessary to implement paragraphs
6.4 - 6.10 of the HELCOM Guidelines for the Management of Dredged Material at Sea.
2. A tiered approach to testing is recommended. At each tier it will be necessary to determine
whether sufficient information exists to allow a management decision to be taken or whether further testing
is required.
3. As a preliminary to the tiered testing scheme, information required under section 6.3 of the
Guidelines will be available. In the absence of appreciable pollution sources and if the visual determination of
sediment characteristics leads to the conclusion that the dredged material meets one of the exemption criteria
under paragraph 6.3 of the Guidelines, then the material will not require further testing. However, if all or part
of the dredged material is being considered for beneficial uses, then it will usually be necessary, in order to
evaluate these uses, to determine at least some of the physical properties of the material indicated in Tier I.
4. The sequence of tiers is as follows:
- assessment of physical properties
- assessment of chemical properties
- assessment of biological properties and effects
A pool of supplementary information, determined by local circumstances may be used to augment each tier
(cf. section 6.5 of the Guidelines).
5. At each stage of the assessment procedure account must be taken of the method of analysis.
Analysis should be carried out on the whole sediment (< 2mm) or in a fine-grained fraction. If analysis is carried
out in a fine-grained fraction, the results should be appropriately converted to whole sediment (< 2 mm)
concentrations for establishing total loads of the dredged material. Additional information (e.g. as regards
storage and pre-treatment of samples, analytical procedures, analytical quality assurance) should be included
in relevant HELCOM Monitoring Manual.
6. The physical composition of samples, and therefore the chemical and biological properties,
can be strongly influenced by the choice of sampling sites, the method of sampling and sampling handling.
These possible influences should be taken into account when evaluating data.
Tier I: PHYSICAL PROPERTIES
Physical analyses are important because they help to indicate how the sediment may behave during dredging
and deposit operations and indicate the need for subsequent chemical and/or biological testing. It is strongly
recommended that the following determinations be carried out:
Determinant
Indicating
grain size analysis (by laser or sieving
methods)
percent solids (dry matter)
Cohesiveness, settling velocity/resuspension potential,
contaminant accumulation potential
density/specific gravity
Consolidation of placed material, volume in situ vs. after
deposit
organic matter (as total organic
carbon)
Potential accumulation of organic associated
contaminants
Page
21
of 39
When dredged material is being considered for beneficial uses, it will also usually be necessary to have
available details of the engineering properties of the material e.g. permeability, settling characteristics,
plasticity and mineralogy.
Tier II: CHEMICAL PROPERTIES
Primary List
List of metals, metalloids and organic/organo-metallic compounds to be determined:
Cadmium (Cd)
Chromium (Cr)
Copper (Cu)
Lead (Pb)
Mercury (Hg)
Nickel (Ni)
Zinc (Zn)
Arsenic
Polychlorinated biphenyl (ΣPCB) congeners - IUPAC nos 28, 52, 101, 118, 138, 153 and 180 (ICES
7).
Polycyclic aromatic hydrocarbons (PAHs). ΣPAH16 and/or ΣPAH9 as a subgroup of ƩPAH16 (at least
the following, but not limited to: anthracene; benzo[a]anthracene; benzo[ghi]perylene;
benzo[a]pyrene;chrysene; fluoranthene; indeno[1,2,3-cd]pyrene; pyrene; phenanthrene).
Tri-butyl tin (TBT) compounds and their degradation products.
As a minimum requirement, national action levels need to be established for the primary list above.
Determination of PCBs, PAHs and Tri-Butyl tin compounds and their degradation products will not be
necessary in circumstances where the sediments are very unlikely to be contaminated with these substances.
The relevant circumstances are:
a) sufficient information from previous investigations indicating the absence of contamination is
available (cf. para 7.5-7.7 in the HELCOM Guidelines for Management of dredged Material at
Sea); or
b) - there are no known significant sources (point or diffuse) of contamination or historic
inputs; and
- the sediments are predominantly coarse; and
- the content of total organic carbon is low.
Secondary List
Based upon local information of sources of contamination (point sources or diffuse sources) or historic inputs,
other determinants may require analysis, for instance:
Other chlorobiphenyls
Organochlorine pesticides
Organophosphorus pesticides
Tri-phenyl tin (TPhT)
Other anti-fouling agents
Petroleum hydrocarbons
Polychlorinated dibenzodioxins (PCDDs)/polychlorinated dibenzofurans (PCDFs)
Phthalates (DEHP and optionally - DBP/BBP)
Page
22
of 39
In deciding which additional individual organic contaminants to determine, reference should be made to
existing priority substance lists, such as those prepared by HELCOM
5
and the EU
6
(as applicable).
Normalisation
It is recommended that normalised values of contaminants should be used to enable a more reliable
comparison of contaminant concentrations in dredged material with those in sediments at deposit or
reference sites, as well as with action levels. The normalisation procedure (see Technical Annex II) used within a
regulatory authority should be consistent to ensure effective comparisons.
Additionally in order to be in the position to anticipate the effects of contaminants absorbed on sediment
particles on deposit or filter feeders it is important to have information on the contaminant concentration of
the relevant fine fraction (e.g. less than 63 µm or 20 µm).
Analytical Techniques
Reference should be made to the Technical Annexes of the relevant HELCOM Monitoring manual and ISO/EN
methods for recommended analytical techniques.
Tier III: BIOLOGICAL PROPERTIES AND EFFECTS
In a significant number of cases the physical and chemical properties described above do not provide a direct
measure of the biological impact. Moreover, they do not adequately identify all physical disturbances and all
sediment-associated constituents present in the dredged material. If the potential impacts of the dredged
material to be deposited cannot be adequately assessed on the basis of the chemical and physical
characterisation, biological measurements should be carried out.
The selection of an appropriate suite of biological test methods will depend on the particular questions
addressed, the level of contamination at the dredging site and the degree to which the available methods
have been standardised and validated.
To enable the assessment of the test results, an assessment strategy should be developed with regard to
granting a permit authorising deposit at sea. The extrapolation of test results on individual species to a higher
level of biological organisation (population, community) is still very difficult and requires good knowledge of
assemblages that typically occur at the sites of interest.
1. Toxicity bioassays:
The primary purpose of toxicity bioassays is to provide direct measures of the effects of all sediment
constituents acting together, taking into account their bioavailability. For ranking and classifying the
acute toxicity of harbour sediment prior to maintenance dredging, short-term bioassays may often
suffice as screening tools.
To evaluate the effects of the dredged material, acute bioassays can be performed with pore water, an
elutriate or the whole sediment In general, a set of 2-4 bioassays is recommended with organisms from
different taxonomic groups and different trophic levels (e.g. crustaceans, molluscs, polychaetes, bacteria,
echinoderms);
In most bioassays, survival of the test species is used as an endpoint. Chronic bioassays with sub-
lethal endpoint (growth, reproduction etc) covering a significant portion of the test species life
cycle may provide a more accurate prediction of potential impact of dredging operations.
However, standard test procedures are still under development.
5
List of Harmful Substances according to Annex I of the HELSINKI Convention and the priority hazardous substances
contained in HELCOM Recommendation 31-E/1
6
Directive 2013/39/EU of the European Parliament and of the Council of 12 August 2013 amending Directives 2000/60/EC
and 2008/105/EC as regards priority substances in the field of water policy
Page
23
of 39
The outcome of sediment bioassays can be unduly influenced by factors other than sediment-
associated chemicals. Confounding factors like ammonia, hydrogen sulphide, grain size, oxygen
concentration and pH should therefore be determined during the bioassay.
Guidance on the selection of appropriate test organisms, use and interpretation of sediment bioassays
is given by e.g. USACE/EPA (1991/1994) and CEDA & IADC (2008) while guidance on sampling of
sediments for toxicological testing is given by e.g. ASTM (1994).
2. Biomarkers:
Biomarkers may provide early warning of more subtle (biochemical) effects at low and sustained levels
of contamination. Most biomarkers are still under development but some are already applicable for
routine application on dredged material (e.g. one which measures the presence of dioxin-like
compounds - Murk et al., 1997) or organisms collected in the field (e.g. DNA strand/breaks in flat fish).
3. Microcosm experiments:
There are short-term microcosm tests available to measure the toxicant tolerance of the community
e.g. Pollution Induced Community Tolerance (PICT) (Gustavson and Wangberg, 1995)
4. Mesocosm experiment:
In order to investigate long-term effects, experiments with dredged material in mesocosms can be
performed, for instance to study the effects of PAHs in flatfish pathology. Because of the costs and time
involved these experiments are not applicable in the process of authorising permits but are useful in
cases where the extrapolation of laboratory testing to field condition is complicated r environmental
conditions are very variable and hinder the identification of toxic effects as such. The results of these
experiments would be then available for future permitting decisions.
5. Field observation of benthic communities:
Monitoring in the surrounding of the deposit site of benthic communities e.g. in situ (fish, benthic
invertebrates) can give important clues to the condition of marine sediments and are relevant as a
feed-back or refinement process for authorising permits. Field observations give insight into the
combined impact of physical disturbance and chemical contamination. Guidelines on the monitoring of
benthic communities are provided by e.g. OSPAR, ICES, HELCOM.
6. Other biological properties:
Where appropriate, other biological measurements can be applied in order to determine e.g. the
potential for bioaccumulation and for tainting.
SUPPLEMENTARY INFORMATION
The need for further information will be determined by local circumstance and may form an essential part of
the management decision. Appropriate data might include: redox potential, sediment oxygen demand, total
nitrogen, total phosphorus, iron, manganese, mineralogical information or parameters for normalising
contaminant data (e.g. aluminium, lithium, scandium cf. Technical Annex II). Consideration should also be
given to chemical or biochemical changes that contaminants may undergo when deposited of at sea.
Page
24
of 39
Literature References related to Technical Annex I
ASTM, 1994. Standard guide for collection, storage, characterisation and manipulation of sediment for
toxicological testing. American Society for Testing and Material, Annual Book of Standards. Vol. 11.04,
E1391-96.
EPA/CE, 1991. Evaluation of Dredged Material Proposed for Ocean Disposal: Testing Manual
EPA-503/8-91/001. US-EPA Office of Water (WH-556F).
EPA/CE, 1998. Evaluation of Dredged Material Proposed for discharge in Waters of the US. Testing Manual
(Draft): Inland Testing Manual EPA 823-B-98-004.
EPA, Office of Water, 2001. Methods for Collection, Storage and Manipulation of Sediments for Chemical
and Toxicological Analyses: Technical Manual EPA-823-F-01-023.
International Association of Dredging Companies (IADC)/Central Dredging Association (CEDA), 1997.
Environmental Aspects of Dredging. Guide 3 (Investigation, Interpretation and Impact). ISBN 90-75254-08-
3.
International Maritime Organization (IMO) 2003. Waste Assessment Guidance - Selection and analysis of
physical and chemical parameters for the assessment of dredged material quality, Report of the Scientific
Group of the LONDON Convention.
IOC - UNEP - IMO, 2000. Global Investigation of Pollution in the Marine Environment (GIPME 2000):
Guidance on Assessment of Sediment Quality, Pub. No. 439/00.
Gustavson, K. and Wangberg, S.A.,1995. Tolerance induction and succession in microalgae communities
exposed to copper and atrazine. Aquatic Toxicology. 32: 283-302.
HELCOM, 1997. Manual for Marine Monitoring in the Cooperative Monitoring in the Baltic Marine
Environment (COMBINE Programme) of HELCOM. Part C Programme for Monitoring of Eutrophication
and its Effects. Annex C-4: Directives for sampling and analysis of hydrographic, chemical and biological
variables. Annex C-8: Soft bottom macrozoobenthos.
Murk et al., 1996. Chemical-activated luciferase gene expression (CALUX): a novel in vitro bioassay for Ah
receptor active compounds in sediments and pore water. Fund. & Applied Tox. 33: 149-160.
OSPAR, 1997 (available from the OSPAR website):
JAMP Eutrophication Monitoring Guidelines: Benthos - Technical Annex 1 (Hard-bottom
macrophytobenthos and hard-bottom macrozoobenthos) - Technical Annex 2 (Soft-bottom
macrozoobenthos)
OSPAR 2002. JAMP Guidelines for Monitoring Contaminants in Sediments
Rees, H.L., C. Heip, M. Vincx and M.M. Parker, 1991. Benthic communities: use in monitoring point-source
discharges. ICES Techniques in Marine Environmental Sciences No. 16.
Rumohr, H.,1990. Soft-bottom macrofauna: collection and treatment of samples. ICES Techniques in
Marine Environmental Sciences No. 8.
Page
25
of 39
Technical Annex
II
7
Normalisation of Contaminants Concentrations in
S
e
di
me
nts
This Annex provides guidance on the application of methods to normalise contaminant concentrations in
sediments
1. Introduction
Normalisation is defined here as a procedure to correct contaminant concentrations for the influence of the
natural variability in sediment composition (grain size, organic matter and mineralogy). Most natural and
anthropogenic substances (metals and organic contaminants) show a much higher affinity to fine particulate
matter compared to the coarse fraction. Constituents such as organic matter and clay minerals contribute to
the affinity to contaminants in this fine material.
Fine material (inorganic and organic) and associated contaminants are preferentially deposited in areas of low
hydrodynamic energy, while in areas of higher energy, fine particulate matter is mixed with coarser sediment
particles which are generally not able to bind contaminants. This dilution effect will cause lower and variable
contaminant concentrations in the resulting sediment. Obviously, grain size is one of the most important
factors controlling the distribution of natural and anthropogenic components in sediments. It is, therefore,
essential to normalise for the effects of grain size in order to provide a basis for meaningful comparisons of
the occurrence of substances in sediments of variable granulometry and texture within individual areas,
among areas or over time.
When analysing whole sediment (i.e. < 2mm fraction) for spatial distribution surveys, the resulting maps give a
direct reflection of the sea bed sediments. However, in areas with varying grain size distributions, a map of
contaminant concentrations will be closely related to the distribution of fine grained sediments, and any
effects of other sources of contaminants, for example anthropogenic sources, will be at least partly obscured
by grain size differences. Also in temporal trend monitoring, differences in grain size distribution can obscure
trends. If samples used for a spatial survey consist predominantly of fine material, the influence of grain size
distribution is of minor importance and may probably be neglected.
2. Normalisation procedures
Two different approaches to correct for variable sediment compositions are widely used:
a. Normalisation can be performed by relating the contaminant concentration with components
of the sediment that represents its affinity for contaminants, i.e. binding capacity. Such co-
factors are called normalisers (cf. section 4). Normalisation can be performed by simple
contaminant/normaliser ratios or linear regression. Another procedure takes into account that
the coarse sediment fraction contains natural metal concentrations in the crystal structure before
the normalisation is performed (see section 5). Combinations of co-factors, possibly identified
from multiple regression analysis, can be used as normalisers.
b. Isolation of the fine fraction by sieving (e.g. <20 µm, <63 µm) can be regarded as a physical
normalisation to reduce the differences in sediment granulometric compositions and is
applicable to both metals and organic contaminants (Ackermann et al. 1983; Klamer et al. 1990).
Consequently the coarse particles, which usually do not bind anthropogenic contaminants and
dilute their concentrations, are removed from the sample. Then, contaminant concentrations
measured in these fine fractions can be
7
Technical Annex 5 - Normalisation of contaminant concentrations in sediments - to the JAMP Guidelines for
monitoring contaminants in sediments
Page
26
of 39
directly compared. Subsequently, the differences in sediment composition due to geochemical
nature remaining after sieving can be further corrected for by the use of co-factors. Thus, sieving
is a first powerful step in normalisation.
3. Limitations of normalisation
Clearly, normalisation procedures may not apply equally well to all elements at all sites; especially
important in this respect are elements that participate in diagenetic reactions. In cases where there is a lack
of full understanding of the geochemical processes operating care should be taken when normalising for
grain size differences. These processes can create important natural enrichment of metals at the sediment
surface, as a result of the surficial recycling of oxihydroxides or deeper in the sediment as the result of co-
precipitation of the metals with sulphides (cf., e.g., Gobeil et al. 1997), which cannot be accounted for by
normalisation.
There is no evidence that normalised data are more appropriate for ecotoxicological interpretation than
non-normalised data. However, the matter deserves further investigation.
4. Normalisation with co-factors
a. The binding capacity of the sediments can be related to the content of fines (primary factor) in
the sediments. Normalisation can be achieved by calculating the concentration of a contaminant
with respect to a specific grain-size fraction such as <2 µm (clay), <20 µm or <63 µm.
b. As the content of fines is represented by the contents of major elements of the clay fraction
such as aluminium (Windom et al. 1989) or an appropriate trace element enriched in that fraction
such as lithium (Loring 1991), these can also be used as co-factor (secondary). Both, aluminium
and lithium behave conservatively, as they are not significantly affected by, for instance, the early
diagenetic processes and strong redox effects frequently observed in sediments. Problems may
occur in when the sediment is derived from glacial erosion of igneous rocks, with significant
amounts of aluminium present in feldspar minerals contributing to the coarse fraction. In such
cases, lithium may be preferable (Loring 1991).
c. Organic matter, usually represented by organic carbon, is the most common co-factor for
organic contaminants due to their strong affinity to this sediment component. Trace metals can
be normalised using the organic carbon content (Cato 1977) but would require further
explanation due to the non-conservative nature of organic matter.
C
Sand
C
ss
C
s
Slope PL=dC/dN
C
x
N
x
N
s
N
ss
Co-factor i.e.
normaliser
Figure 1: Relation between the contaminant C and the cofactor N (see text).
Page
27
of 39
5. Theory
The general model for normalisation taking into account the possible presence of contaminants and cofactors
in the coarse material is given in figure 1 (Smedes et al.1997). C
x
and N
x
represent the co-factor and the
contaminant contents, respectively, in pure sand
.
These intercepts can be estimated from samples without
fines and organic material. The line of regression between the contaminant and co-factor will originate from
that point. That means that regression lines of sample sets with a different pollution level and consequently
different slopes will have this point in common (i.e. pivot point). When this pivot point is known only one
sample is required to estimate the slope. This allows determination of the contaminant content for any
agreed
(preselected) co-factor content (N
ss
) by interpolation or extrapolation. The slope for a sample with a
contaminant content C
s
and a cofactor content of N
s
can be expressed as follows:
PL =
dC
=
C
s
-
C
x
.................................................................................................(1)
dN
N
s
N
x
The extrapolation to an agreed co-factor content, N
ss
, follows the same slope:
PL =
dC
=
C
s
-
C
x
=
C
ss
-
C
x
..............................................................................(2)
dN
N
s
N
x
N
ss
N
x
Rewriting gives the contaminant content, C
ss
, that is normalised to N
ss
:
N
ss
-
N
x
C
ss
=
(
C
s
-
C
x
)
N
s
-
N
x
+
C
x
...................................................................................(3)
Results of different samples normalised to the agreed N
ss
can be compared directly.
Normalisation by this model can be applied with different cofactors. Here primary and secondary cofactors
can be distinguished. A primary cofactor like clay or organic carbon is not present in the coarse fraction and
consequently has no intercept (N
x
=0). Al and Li are present in the coarse fraction and therefore are considered
to be secondary cofactors. Provided N
x
and C
x
are known, the model allows recalculation of total
samples to
a co-factor content usually found in sieved fractions, either <20 or <63µm. However such an extrapolation
for a coarse grained sample will be associated with a large error due to the uncertainty of the intercepts and
the analysed parameters. For a more fine grained sample, the uncertainty of the normalised result is much
lower than for normalisation of a sieved fraction to the agreed cofactor content and will result in a more
accurate result. The model presented also applies to the normalisation of organic contaminants
using organic
carbon but in that case the intercepts N
x
and C
x
will not differ significantly from zero.
Principally, the result allows comparison of data of total and sieved samples, irrespective the sieving diameter
but the error has to be taken into account. Through propagation of errors the standard error of the result
can
be calculated from the analytical variation and the natural variation of the intercept N
x
. Results can
therefore always be reported with a standard deviation.
6. Considerations on co-factors
The clay mineral content is the most important cofactor for trace metals. In the model above the N
x
will be
zero for clay and only the intercept due to the content of the trace metal in the coarse fraction (C
x
) has to be
taken into account. However, current intercomparison exercises do not include this parameter. Presently
other parameters such as aluminium or lithium are used to represent the clay content.
The aluminium content in the sandy fraction may vary from area to area. For some areas aluminium contents
in the sandy fractions are found at the same level as found in the fines (Loring, 1991) and therefore the
intercept N
x
becomes very high. In equation (3) this implies that the denominator is the result of subtracting
Page
28
of 39
two large numbers, that is the normaliser content in the sample (N
s
) and the normaliser content in only sand
(N
x
). Consequently, due to their individual uncertainties, the result has an extremely high error. Obviously,
Page
29
of 39
normalisation with low intercepts is more accurate. Much lower intercepts are found if partial digestion
methods are used that digest the clay minerals, but not the coarse minerals. Using partial digestion, the
spatial variability of the results of aluminium analyses in the sandy fraction has been found to be much smaller
than with total methods. Although normalising concentrations of contaminants in fine grained material will
always give more accurate results, an error calculation will identify whether using coarse samples (and total
methods, e.g. HF, X-ray fluorescence) allows the requirements of the program to be met.
For most areas the lithium content in the sandy fraction is much lower than in the fine fraction. In addition,
results from partial digestion and total methods do not differ significantly. There is only little spatial variability
of the lithium content in the sandy fraction. Generally, compared to aluminium, more accurate normalised
data can be expected using lithium.
As for clay, no intercept (N
x
) applies for organic matter, which is usually represented by organic carbon.
Organic matter also occurs in the coarse fraction but is even then a cofactor that contributes to the affinity
for contaminants, whereas the aluminium in the coarse fraction does not. Furthermore, organic matter in a
sample is not always well defined as it can be composed of material with different properties. The most
variable properties will be found in the organic matter present in the coarse fraction, i.e. that not associated
with the fines. In fine sediments or in the sieved fine fractions the majority of the organic matter is associated
with the mineral particles and it is assumed to be of more constant composition than in the total sample. In
addition, the nature of the organic matter may show spatial variation. For samples with low organic carbon
content close to the detection limit, normalisation using this cofactor suffers from a large relative error. This
results from the detection limit and the insufficient homogeneity that cannot be improved due to the limited
intake mass for analysis.
For further interpretation of data the proportion of fines determined by sieving can be useful. Provided, there
are no significant amounts of organic matter in coarse fractions, the proportion can be used as normaliser.
The error in the determination of fines has to be taken into account and will be relatively high for coarse
samples.
7. Considerations on contaminants
Almost all trace metals, except mercury and in general also cadmium, are present in the coarse mineral matrix
of samples. The metal concentrations show a spatial variability depending on the origin of the sandy material.
In sandy sediments, partial digestion techniques result in lower values than are obtained from total digestion
techniques. This implies that partial digestion results in lower intercepts (pivot point is closer to the zero).
However, the partial digestion must be strong enough so the clay will be totally digested (as is the case with
HF digestion techniques), and the measured aluminium content remains representative for the clay. It was
demonstrated that analyses of fine material gave similar results for several trace elements using both total
and strong partial methods (Smedes et al. 2000, QUASH/QUASIMEME intercalibrations).
In general, correlations of organic contaminants with organic carbon have no significant intercept. Obviously a
normalised result from a coarse sample will show a large error as due to the dilution by sand the
concentrations are often close or even below the detection limit. Presently, organic carbon is usually applied
for normalisation of PAHs. It should be recognised that due to the possible presence of undefined material,
for example soot or ash, elevated PAH concentrations may occur in specific fractions that might have limited
environmental significance. Although this needs further investigation, existing results indicate that PAH
concentrations in the sieved fractions are not affected significantly.
Page
30
of 39
8. Isolation of fine fractions for analyses
The Sample preparation
Samples must be sieved at 2 mm as soon as possible after sampling to remove large detritus and benthic
organisms. Otherwise during further sample handling like storage, freezing or ultrasonic treatment, biotic
material will deteriorate and become part of the sediment sample. Until the final sieving procedure that
isolates the fines, the sample can be stored at 4°C for about a week and up to 3 months when frozen at
20°C, although direct wet sieving is preferred. For prolonged storage freeze-drying of samples can be
considered. In this case contamination and losses of contaminants during freeze-drying have to be checked.
Air-drying is not appropriate due to high contamination risks. Besides, samples may be difficult to be
disaggregate and mineral structures may be affected.
Requirements for Sieving
A wet sieving procedure is required to isolate the fine-grained fractions (<63 µm or <20 µm). Wet sieving re-
suspends fine particles that would otherwise remain attached to coarser particles in the sample. Sediments
should be agitated during sieving to prevent to disaggregate agglomerates of fines and to prevent clogging
of the mesh. Freeze-dried samples need to be re-suspended using ultrasonic treatment. Seawater, preferably
from the sampling site, should be used for sieving as it reduces the risk of physico-chemical changes in the
sample i.e. losses through leaching or contamination. Furthermore seawater assists the settling of fine
particles after the sieving. If water from the sampling site is not available, then seawater of an unpolluted site,
diluted with deionised water to the required salinity, can be used. The amount of water used for sieving should
be kept to a minimum and be reused for sieving subsequent batches.
To minimise or prevent contamination it is recommended to use large sample amounts of sediment for
sieving. No significant contaminant losses or contamination was detected when at least 25 g of fine fraction
is isolated. (QUASH).
Methodology
Both automated and manual methods are available for sieving. A video presentation of these methods can be
provided by the QUASH Project (QUASH 1999).
The automatic sieving method pumps seawater over a sieve that is clamped on a vibrating table (Klamer
et al. 1990). The water passing the sieve is lead to a flow-through centrifuge that retains the sieved particles
and the effluent of the centrifuge is returned to the sieve by a peristaltic pump. Large sample amounts, up
to 500 g, can be handled easily.
The second method is a manual system sieving small portions 20-60 g using an 8-cm sieve in a glass beaker
placed in an ultrasonic bath (Ackermann et al. 1983). Particles are isolated from the water passing the
sieve by batch wise centrifugation. The water can be reused for a subsequent batch of sediment. In case
of sandy samples, when large amounts of sediments have to be sieved, removal of the coarse material by a
pre-sieving over e.g. 200-µm mesh can facilitate the sieving process.
Isolated fine fractions have to be homogenised thoroughly, preferably by a ball mill, as centrifugation
produces inhomogeneous samples due to differences in settling speed of different grain-size fractions.
9. Recommendations
1. For both temporal trend and spatial monitoring, it would be ideal to analyse samples with equal
composition. This could be confirmed by determination of co-factors Al, Li, OC and parameters of the
grain size distribution (e.g. clay content, proportion <20um, proportion <63um). However, this situation
will not always occur, particularly in the case of spatial surveys.
2. New temporal trend programs should be carried out by the analysis of fine sediments or a fine-grained
fraction, isolated by sieving. Existing temporal trend programs could be continued using existing
procedures, provided that assessment of the data indicates that the statistical power of the programs
Page
31
of 39
is adequate for the overall objectives.
3. Contaminant concentrations in whole sediments can be subjected to normalisation using co-factors
for organic matter, clay minerals etc., taking into account the presence of both co-factors and target
contaminants in the mineral structure of the sand fraction of the sediment. Taking into account these
non-zero intercepts of regressions of contaminant concentrations with co-factors, normalisation to
preselected co-factor content will reduce the variance arising from different grain sizes. Normalised
values for sandy sediments will have greater uncertainties than for muddy sediments. The propagated
error of the variables used for normalisation may be unacceptable high for sandy sediments, if both
contaminant and co-factor concentrations are low, particularly when approaching detection limits. In
that case, in order to draw reliable maps, alternative procedures, such as sieving, need to be used to
minimise the impact of this error structure.
4. Variance arising from grain size differences can be reduced in a direct way by separation of a fine
fraction from the whole sediment. Spatial distribution surveys of the concentrations of contaminants in
separated fine fractions can be used to prepare maps which will be much less influenced by grain size
differences than maps of whole sediment analyses. There will still be some residual variance arising from
differences in the composition (mineralogy and organic carbon content) of the sediments.
5. The natural variance of sample composition will be smaller in the fraction <20 µm than in the fraction
<63 µm. Therefore, the fraction <20 µm should be preferred over the fraction <63 µm. However,
separation of the fraction <20 µm can be considerably more laborious than the separation of the
fraction <63 µm and might be an obstacle to its wide application. For this practical reason, the fraction
<63 µm is an acceptable compromise for both temporal trend and coordinated large scale spatial
surveys.
6. The preferred approach for preparing maps of the spatial distribution of contaminants in sediment
consists of two steps: analyses of contaminants in fine sediments or in the fraction <63 µm, followed
by normalisation of analytical results using co-factors (see section 4). Current scientific knowledge
indicates that this procedure minimises the variances arising from differences in grain size, mineralogy
and organic matter content. Application of this two-tiered approach to fractions <20 µm gives results
that can be directly compared to results found by normalisation of concentrations measured in fractions
<63 µm. This approach should give consistent and comparable data sets over the ICES/HELSINKI area.
Maps of contaminant levels in fine sediments should be accompanied by maps of the co-factors in the
whole sediments.
7. In order to clarify aspects of data interpretation, analytical data for field samples should be
accompanied by information on limits of detection and long term precision. In order to contribute to
environmental assessment, data for field samples should include the grain size distribution, as a
minimum the proportion of the analysed fraction in the original whole sediment.
10. References:
Ackermann, F., Bergmann, H., and Schleichert, U. (1983) Monitoring of heavy metals in coastal and
estuarine sediments - A question of grain-size: <20 µm versus <60 µm. Environmental Technology Letters,
4: 317-328.
Cato, I. (1977): Recent sedimentological and geochemical conditions and pollution problems in two marine
areas in south-western Sweden. Striae 6, 158 pp. Uppsala.
Gobeil, C., MacDonald, R. W. & Sundby, B. (1997): Diagenetic separation of cadmium and manganese in
suboxic continental margin sediments. Geochim. Cosmochim. Acta 61, 4647-4654.
Klamer, J. C., Hegeman, W. J. M. & Smedes, F. (1990): Comparison of grain size correction procedures for
organic micropollutants and heavy metals in marine sediments. Hydrobiologia 208, 213-220.
Loring, D. H. (1991): Normalization of heavy-metal data from estuarine and coastal sediments. ICES J. mar.
Sci. 48, 101-115.
Page
32
of 39
QUASH (1999) Sediment Sieving Techniques, QUASH Project Office, FRS Marine Laboratory, PO Box 101,
Victoria Road, Aberdeen, AB11 9DB, Scotland
Smedes, F. (1997) Grainsize Correction Procedures, Report of the ICES Working Group on Marine Sediments
in Relation to Pollution. ICES CM 1997/Env:4, Ref. E, Annex 6.
Smedes, F., Lourens, J., and Wezel, van A. (1997) Zand, Slib en Zeven, Standardisation of contaminant
contents in marine sediments, Report RIKZ-96.043 (Dutch), ISSN 0927-3980, RIKZ, PO Box 20907, 2500 EX,
The Hague.
Smedes, F. Davies, I.M., Wells, D., Allan, A., Besada, V. (2000): Quality Assurance of Sampling and Sample
Handling (QUASH) - Interlaboratory study on sieving and normalisation of geographically different
sediments; QUASH round 5 (sponsored by the EU Standards, Measurements and Testing Programme)
Windom, H. L., et al. (1989): Natural trace metal concentrations in estuarine and coastal marine sediments
of the southeastern United States. Environ. Sci. Technol. 23, 314-320.
Appendix
Testing normalisation methods
As normalisation should correct for sediment composition, a criterion for an adequate normaliser is that
after normalisation of equally polluted sediment samples with different grain size distributions, the results
should not differ significantly. However, sample sets to test normalisation approaches for this criterion are
scarce. An alternative approach is to take one sample and to produce subsamples with varying grain size
distributions (Smedes 1997, Smedes et al. 1997, Smedes et al. 2000). Both the fine and coarse subsamples
are analysed for contaminants and potential normalisers. In this way a higher variability for the normaliser
concentrations, i.e. a worst case than ever will occur in nature, can be obtained which provides a sensitive
test for the usefulness of potential normalisers.
Page
33
of 39
Technical Annex
III
Introduction
Best Environmental Practice (BEP)
This Technical Annex was prepared bearing in mind that, although the guidelines strictly only apply to the
deposit of dredged material, Contracting Parties are encouraged also to exercise control over dredging
operations.
This Technical Annex has as its aim to provide guidance to national regulatory authorities, operators of
dredging vessels and port authorities on how to minimise the effects on the environment of dredging and
deposit operations. Careful assessment and planning of dredging operations are necessary to minimise the
impacts on marine species and habitats.
The items given as BEP under the different headings of this Technical Annex are given as examples. Their
applicability will generally vary according to the particular circumstances of each operation and it is clear that
different approaches may then be appropriate. More detailed information on dredging techniques and
processes can be found in Guide 4 of the IADC/CEDA series on Environmental Aspects of Dredging.
BEST ENVIRONMENTAL PRACTICE TO OPTIMISE
THE DEPOSIT OF DREDGED MATERIAL AT SEA
MINIMISE
THE
EFFECTS CAUSED
BY
THE DEPOSIT
OF
DREDGED
MATERIAL
MINIMISE
THE
IMPACTS
OF
DREDGING
OPTIMISE
THE
DEPOSITED
QUANTITIES
IMPROVE
SEDIMENT QUALITY
Point A - Minimisation of the effects caused by the deposit of dredged material - is comprehensively described
in the main body of these guidelines; Point B ‘Optimisation of the deposited quantities; Point C
‘Improvement of sediment quality and Point D ’Minimise the Impacts of Dredging are requirements
resulting from Annex V to the HELSINKI Convention (see § 3.5 of the HELCOM Guidelines for the Management
of Dredged Material at Sea), and, in addition, are very relevant to the prevention of pollution of the marine
environment resulting from the deposit of dredged materials. Descriptions of BEP in relation to these activities
are given at Appendices I and II.
Page
32
of 39
OPTIMISE THE DEPOSITED QUANTITIES
APPENDIX I
KEEP VOLUME OF DREDGED MATERIAL MINIMAL IMPROVE DREDGING PROCESS
MINIMISE NEED FOR DREDGING OPTIMISE DREDGING OPERATIONS MANAGEMENT
In fluid mud areas: introduce the concept of
Navigable depth based on:
- physico-chemical evaluation of the sediment
(including rheometry and densimetry)
- full scale trials
BEP: Dredging only the amount of
material required for maintaining a particular
density level to allow navigation. This may require
e.g. continuous underway measurement of sediment
density by using a nuclear transmission gauge or
measurement of shear forces.
In areas with sandy waves etc.
BEP: - selective dredging of sand waves and
other mobile sand structures
Hydraulic Engineering
BEP: - use of hydraulic structures to
reducesedimentation
Accurate monitoring of dredged depths at an
appropriate frequency
BEP: - accurate positioning systems e.g.:
- microwave systems
- radiowave technology
- DGPS
- apply rapid survey equipment
- continuous measurement systems
- echosounders
- swath/multibeam systems
Accurate survey systems
(see column 1: Accurate monitoring)
Availability of survey data on board
BEP: - on-line visualisation of updated
bathymetric charts, including topographic
data, coastlines, deposit areas, dredge
position, dredge head position
- tidal information
Process evaluation
BEP: - visualisation/evaluation of dredged
tracks/profiles/zones
- dredging intensity chart
- in case of muddy material, sand and
gravel: establish optimum overflow time
by analysis of load diagrams
Effective dredging process control
BEP: - Continuous on-line measurements and
presentation e.g.
- of area, heading, speed of the dredgers
and position of the suction
head/buckets/cutter/backhoe/grab/
wheel/...
- measurement of mixture velocity and
concentration
- measurement of macro production (load
diagram)
- hopper-measurement system monitoring
the filling process
Output improving techniques
BEP: - best suited suction head/cutters wheel/
backhoe/buckets
- submerged dredge-pumps
- degassing installations
- etc.
Selective dredging techniques
BEP: - selective dredging to e.g. separate
contaminated material (e.g. freeze”
dredging)
See IADC/CEDA report referenced in the Introduction
for further information on this topic
Page
33
of 39
APPENDIX
II
IMPROVE SEDIMENT QUALITY
MINIMISE THE IMPACTS OF DREDGING
IN SITU BEFORE DREDGING AND AFTER DEPOSIT IN THE HOPPER
Improve physical aspects (cohesion, consistency,
density) of dredged material
BEP: - increase sediment density by physical
means e.g. vibration
Mechanical separation
BEP: - hydrocyclones for separation of
granulometric fractions
- flotation
- dewatering (under development)
(consider potential problems with process water and
associated contaminants e.g. re-circulation will reduce
problems
Minimise increases in turbidity
BEP: - use excavation tools /dredger heads
appropriate to minimise turbidity
- use silt screens/shields
- minimise overflow by e.g. recirculation
of overflow water
- use specially designed dredgers to
dredge contaminated sediments
- avoid the use of dredgers which
introduce large amounts of suspended
sediments into the water column where
this may lead to problems with oxygen
depletion or contamination e.g.
agitation dredgers
Minimise oxygen depletion
BEP: Avoid periods when dredging
induced turbidity will lead to
unacceptable reductions in oxygen levels
due to high temperatures
Page
34
of 39
HELCOM Reporting Format for Management of Dredged Material at Sea
Attachment 1
Explanatory notes for 2014 revised reporting format for management of dredged
material at sea
GENERAL
1. HOD 51-2016 adopted this revised reporting format for use from 2017 onwards.
2. National data should be entered in the respective sheets of the accompanying spreadsheet by
following the instructions given below.
3. Deposit site would be described in Sheet 1a. Only one row per deposit site is allowed
4. Material originating from different locations but deposited of at the same deposit site described in
Sheet 1a should be described in separate lines in sheets 2 and 3.
5. Please do not alter the format of the spreadsheet (e.g. by insertion of new columns or rows), but inform
the Secretariat of any problems you may encounter.
6. Please indicate clearly the reference for all additional information by using sheet 7 of the spreadsheet.
7. Each deposit site will be assigned with unique HELCOM ID/code, which must not change from year to
year.
8. The location of deposit sites of each Contracting Party, should be supplied in ArcGIS compatible shape
files (in ETRS89LAEA projection) clearly showing the HELCOM codes (as given in the data tables), the
location and any other relevant information in the attribute table of the shapefile.
GUIDANCE FOR REPORTING
9. The data should be entered by using the continental decimal (with a space as 1000 separator and a
comma as decimal separator) with the maximum number of digits available (i.e. with maximum number
of digits after the comma) and taking into account the unit given in the column header. This will ensure
correct calculations for preparing total amounts. The pre-defined number format in all data cells ensures
that the values will be displayed and printed.
10. Missing information should be indicated as follows:
NI no information
ND not determined
< less than (please state in the text.doc file the value of the respective limit)
EX exempted from analyses according to the HELCOM Guidelines for the Management of
Dredged Material at Sea (cf. Section 6.3 of the Guidelines)
11. Please submit your data to the HELCOM Secretariat HELCOM.Secretariat@helcom.fi by 1 October of
the year following the dredging activity. It is intended that HELCOM Secretariat will combine the
information to a database and will make it available online via HELCOM website.
Page
35
of 39
Instructions for reporting data per sheet:
cf. attached MS-Excel Spreadsheet
Sheet 1 Permits
Contracting Party
Select correct option from dropdown list provided
Year
Year of deposit activity.
Report ID
Unique ID, Contracting party-Year e.g. PL-2014
Number of permits issued or regulated
under other means
Number of permits issued or regulated under other means in year prior to
reporting year. By ‘other means any kind of relevant national regulation
is meant, that is used for
permitting/licensing/allowing
deposit operation
Material licensed or regulated by other
means (tonnes - dry weight)
See sheet 7 in the attached MS Excel Spreadsheet for conversion from
wet weight to dry weight
Dredged material deposited (tonnes -
dry weight)
Amount actually deposited
Notes
Information of relevance
Sheet 1a Deposit sites (optional)
proposed by HELCOM, based on IMO LC/LP Tabular reporting format
Report ID
Report code: Contracting party-Year, e.g. PL-2014
PL country of origin
2014 - year
National Deposit site code
Code for a particular location remains the same from year
to year., e.g.
001 deposit site code
HELCOM Deposit site ID
Unique ID, is generated to differentiate separate deposit
sites, with dash separator e.g.
PL-001
PL country of origin
001 deposit site code
Specific national site name
Name should preferably indicate name of water system e.g.
Bay of Gdansk and then type of water system: river,
estuary, harbour, coastal waters, and actual name of the
site etc., e.g. Baltic Proper, Kolobrzeg Harbour waters
Shapefile submitted
Yes/No-field indicating whether spatial data is included as
shapefile (this is recommended) with data submission.
Circular Deposit Site Center Point - Latitude
Area should be reported as GIS Shapefile containing
HELCOM Site ID (See instructions for reporting data per
shapefiles)
Reference Note:
1
Conversion of latitude and longitude coordinates from
degrees, minutes and seconds to decimal degrees can be
accomplished by accessing the U.S. Federal Communications
Commission website at:
Circular Deposit Site Center Point - Longitude
Circular Deposit Site - Radius
Polygonal Deposit Site Coordinate 1 - Latitude
Polygonal Deposit Site Coordinate 1 - Longitude
Polygonal Deposit Site Coordinate 2 - Latitude
Polygonal Deposit Site Coordinate 2 - Longitude
Page
36
of 39
Polygonal Deposit Site Coordinate 3 - Latitude
http://www.fcc.gov/mb/audio/bickel/DDDMMSS-
decimal.html. It is likely that there are many such sites
available to LC/LP member States.
No need to fill coordinates, if those are reported as shapefile
containing geographic area and HELCOM ID
Polygonal Deposit Site Coordinate 3 - Longitude
Polygonal Deposit Site Coordinate 4 - Latitude
Polygonal Deposit Site Coordinate 4 - Longitude
Activity within deposit site (optional)
Contains latitude and longitude coordinates of a pointwise
deposit operation within a deposit site area/licensed area
(polygon or a circular site)
Type of deposit (dumping or placement)
Select correct option from dropdown list provided
Comments
Sheet 1b Dredging site coordinates (optional: If available, shapefile or pointwise location of
dredging site, where dredged material is originated)
HELCOM Dredging site ID
Unique ID for a dredging site to differentiate dredging site
Shapefile submitted
Yes/No-field indicating whether spatial data about dredging site is included
as shapefile (this is recommended)
Latitude
Dredging site latitude and longitude coordinates of a pointwise
dredging operation within a dredging site area/licensed area
(polygon or a circular site)
Longitude
Specific national site name
Name of dredging site.
Sheet 2 Contaminated material (to be filled-in case of depositing contaminated sediments)
HELCOM Deposit site ID
Is used to link to deposit site e.g. PL-001; will be generated automatically
HELCOM Dredging site ID
is generated to differentiate separate deposit operations per deposit site
per year, e.g.
0009 dredged material origin code (e.g. permit #)
Contaminant
Average concentration in the dredged
material (mg/kg dry wt)
National criteria/upper level (mg/kg dry
weight)
Dredged material deposited (tonnes -
dry weight)
Reasons for allowing deposit
Describe reasoning behind granting of approval.
Additional information
Sheet 3 Details of activity (refers to reporting of dredging operations)
HELCOM Deposit site ID
Is used to link to deposit site e.g. PL-001; will be generated automatically
HELCOM Dredging site ID
is generated to differentiate separate deposit operations per deposit site
per year, e.g.
0009 dredged material origin code (e.g. permit #)
Description of dredged material eg silt /
sand / gravel
Describe in general terms, the granulometry of the sediment - % gravel,
sand and silt
Page
37
of 39
Origin, (name of water system dredged)
River, estuary, etc.,
Type of areas dredged
Select correct option from dropdown list provided
Dredging Activity
Select correct option from dropdown list provided
Amount of dredged material deposited
(tonnes - dry weight)
As indicated
Amount of dredged material placed
Quantity for beneficial use (tonnes - dry
weight)
As indicated
Placement (beneficial use)
Select correct option from dropdown list provided
Material exempted from
characterisation (tonnes - dry weight)
As indicated
Notes (e.g. monitoring reports)
monitoring related to dredging activities
Comments
Page
38
of 39
Sheet 4 Contaminant load
HELCOM Deposit site ID
Is used to link to deposit site e.g. PL-001; will be generated automatically
HELCOM Dredging site ID
is generated to differentiate separate deposit operations per deposit site per year,
e.g.
0009 dredged material origin code (e.g. permit #)
Exemption
Yes/No-field indicating whether dredged material is exempted from physical and
chemical characterization (see Guideline paragraph 6.3)
Cd (tonnes dry wt)
Tonnes of cadmium deposited (dry weight)
Hg (tonnes dry wt)
Tonnes of mercury deposited (dry weight)
As (tonnes dry wt)
Tonnes of arsenic deposited (dry weight)
Cr (tonnes dry wt)
Tonnes of chromium deposited (dry weight)
Cu (tonnes dry wt)
Tonnes of copper deposited (dry weight)
Pb (tonnes dry wt)
Tonnes of lead deposited (dry weight)
Ni (tonnes dry wt)
Tonnes of nickel deposited (dry weight)
Zn (tonnes dry wt)
Tonnes of zinc deposited (dry weight)
ΣPAH16 (tonnes dry wt)
Tonnes of USEPA 16 selected selected polycyclic aromatic hydrocarbons deposited,
(dry weight) if data available (see glossary below)
ΣPAH9 (tonnes dry wt)
and/or as a part of PAH16; Tonnes of nine selected polycyclic aromatic
hydrocarbons deposited (dry weight) (see glossary below)
ΣPCB7 (kg dry wt)
Tonnes of IUPAC nos 28, 52, 101, 118, 138, 153 and 180 (ICES 7) deposited (dry
weight)
TBT (kg dry wt)
Kilograms of tributyl tin deposited (dry weight)
DBT (kg dry wt)
Kilograms of dibutyl tin deposited (dry weight)
MBT (kg dry wt)
Kilograms of monobutyl tin deposited (dry weight)
Other contaminants
Contracting Parties are invited to include substances from the Secondary List as
relevant, deposited (dry weight)
Petroleum HC (tonnes dry wt)
Tonnes of petroleum hydrocarbons/oil deposited (dry weight) (see glossary below)
HCB (kg dry wt)
Kilograms of Hexachlorobenzene deposited (dry weight)
χ-HCH (kg dry wt)*
Kilograms of χ-Hexachlorocyclohexane (Lindane) deposited (dry weight)
Σ DDT** (kg dry wt)
Kilograms of total DDT deposited (dry weight) (see glossary below)
TPhT (kg dry wt)
Kilograms of total TPhT deposited (dry weight) (see glossary below)
Page
39
of 39
PCDDs/PCDFs (kg dry wt)
Kilograms of total PCDDs/PCDFs deposited (dry weight) (see glossary below)
DEHP (DBP/BBP) (kg dry wt)
Kilograms of total DEHP (DBP/BBP) deposited (dry weight) (see glossary below)
notes
Any additional relevant information (dry weight)
* α-HCH or β-HCH can be optionally reported
** Ʃ DDT refers to Ʃ of o,p'-DDT; p,p'-DDT; o,p'-DDE; p,p'-DDE; o,p'-DDD; p,p'-DDD“ or Ʃ of 4,4'-DDT, 4,4'-
DDE, 4,4'-DDD, 2,4' DDT, 2,4'-DDD, 2,4'-DDE
Sheet 5 Analyses quality information
Purpose of this sheet is to collect relevant information on national quality assurance procedures, which is
relevant if the data to be used e.g. for HELCOM assessments;
Information to be provided only once (upon request) if there are substantial changes in labs used for analysis
and/or in case data quality information is needed for assessment purposes
Details of limits of detection only required where analysis result is below detection limit.
Analytical quality information for other reported contaminants (from Secondary List) should be also provided
in the same manner as for Primary List of substances
Reference should be made to Part B of the HELCOM Manual for Marine Monitoring (including relevant
Annexes, e.g. B-13 Technical Note on the determination of heavy metals and persistent organic compounds
in marine sediments) and ISO/EN methods for recommended analytical techniques, e.g.
o The monitoring laboratories should have a QA/QC system that follows the requirements of EN
ISO/IEC 17025 "General requirements for the competence of testing and calibration laboratories"
(formerly EN 45001 and ISO Guide 25)
o Limit of detection, quantification or application are validation parameters which describe the
sensitivity of an analytical methods with regard to the detection and quantification of a certain
analyte. Therefore, a number of publications recently provided different approaches to define and
calculate these measures by
instrumental
or
mathematical approaches
(DIN 32645, 1994; EURACHEM,
1992; Ge and Einax, 2000; ICH, 1996; ISO 11843, 1997-2003; ISO/CD 13530, 2003; IUPAC, 1997,
2002).
Sheet 6 Action levels
Action levels should be provided when initially completing new reporting format. Action levels do not need to
be reported again unless they are revised.
Action Level information for other reported contaminants (from Secondary List) should be also provided in
the same manner as for Primary List of substances
Sheet 7 - Additional information for CP
Calculations for wet weight to dry weight
Conversion factors from volume to weight which can be used in the event that density has not been
measured (see Sheet 7 in the attached MS-Excel Spreadsheet for conversion from wet weight to dry weight)
Instructions for reporting data per shapefile:
The areas of deposit sites (Excel sheet 1a, circular / polygonal deposit site coordinates, Excel sheet 3, details of activity,
point coordinates) can be reported using GIS shapefile, which contains the geographic area of the deposit site. The
shapefile should have following information content and format:
- Shapefile should be in ETRS89LAEA projection (EU-INSPIRE compatible projection) (How to define
projection/project shapefile in ArcGIS)
- All circular / polygonal depositsites (Excel sheet 1a) of a contracting party should be reported in one shapefile
- All pointwise activity locations (Excel sheet 3) of a contracting party should be reported in one shapefile
- Each polygon/point in a shapefile should contain the HELCOM Site ID (e.g. PL-2014-001) of the deposit site in the
attribute table column titled
“HELCOM_ID
Shapefiles should be reported simultaneously with the reporting MS Excel sheets
Page
40
of 39
Glossary:
Capital dredging
Capital dredging includes geological material dredged from previously unexposed layers
beneath the seabed and surface material from areas not recently dredged.
Σ DDT
Dichlorodiphenyltricholoethane
(DDT) (CAS no. 50-29-3) is an organochlorinated pesticide;
DDT and related compounds or sum of DDT refer to p,p’-DDT, o,p’-DDT, p,p’-DDE, o,p’-
DDE, p,p’-DDD and o,p’- DDD
Dredged material
Dredged material is sediment dredged from the sea bed, which could consist of e.g.
boulder, clay, sand, rocks.
Harbour
Harbours include enclosed and semi-enclosed docks, docks entrances, marinas, wharves
and unloading jetties
Maintenance
dredging
Maintenance dredging is the dredging required to maintain berths and navigation
channels
at
advertised depth. It includes material dredged from recently deposited by sedimentation
processes in harbour or sea areas
Oil
Total petroleum hydrocarbons (total oil and grease)
C10 C40
Others
This could include e.g. disposals resulting from force majeure or emergency situations or
the disposal of spoiled cargos.
Σ PAH
9
anthracene; benzo[a]anthracene; benzo[ghi]perylene; benzo[a]pyrene; chrysene;
fluoranthene;
indeno[1,2,3-cd]pyrene;
pyrene; phenanthrene
Σ PAH
16
acenaphthene, acenaphthylene, anthracene, benzo[a]anthracene, benzo[b]fluoranthene,
benzo[k]flouranthene, benzo[a]pyrene, benzo[ghi]perylene, chrysene,
dibenz(ah)anthracene, fluoranthene, fluorene, indeno(1,2,3-cd)pyrene, naphthalene,
phenanthrene and pyrene,
PCDDs/PCDFs
Polychlorinated dibenzo-p-dioxins (PCDD) and polychlorinated dibenzofurans (PCDF) are
environmental contaminants detectable in almost all compartments of the global
ecosystem in trace amounts. These compound classes in particular have caused major
environmental concern.
ΣPCB
7
CB 28; CB 52; CB 101; CB 118; CB 138; CB 153; and CB 180
Total PCB
Total PCB is the extraction of the 209 congeners
Petroleum HC
Petroleum hydrocarbons are the primary constituents in oil, gasoline, diesel, and a variety
of solvents and penetrating oils. The petroleum constituents of primary interest to human
health have been the aromatic hydrocarbons (i.e., benzene, ethylbenzene, toluene, and
xylenes), polynuclear aromatic hydrocarbons (PAHs)
DEHP (DBP/BBP)
Phthalates, or phthalate esters, are esters of phthalic acid and are mainly used
as plasticizers
(substances added to plastics to increase their flexibility,
transparency, durability,
and
longevity). Di(2-ethylhexyl) phthalate (DEHP), Di-n-butyl phthalate (DBP) and
Benzylbutylphthalate (BBP) and one of most widely used and raising most environmental
concerns phthalates.
Sea areas
Areas outside harbours i.e. in open, coastal and offshore sea areas
TPhT
Triphenyltin compounds are organotin compounds with the general formula (C
6
H
5
)
3
Sn
X
.
Triphenyltin compounds have been used extensively as algicides and molluscicides in
antifouling products since the 1960s, together with tributyltin compounds and both these
classes of compounds are of local (but not global) environmental concern because they are
persistent organic pollutants
Page
41
of 39
Attachment 2
Explanatory notes for the reporting template of consolidated reporting to LC/LP, carried out by the HELCOM
Secretariat.
Sheet 1 summary
Country
Contracting Party of deposit site
Year
Year of activity
Maintenance (Number of activities)
Number of activities, Maintenance dredging
Capital (Number of activities)
Number of activities, Capital dredging
Maintenance (Amount)
Amount material deposited, Maintenance dredging
Capital (Amount)
Amount material deposited, Capital dredging
Total amount
Total amount of material deposited
Unit
Unit of material deposited (e.g. tonnes - dry weight)
Sheet 2 - details of the sites
Country
Contracting Party of deposit site
Code
HELCOM deposit ID
Latitude
Latitude of deposit site (centroid for polygon and line features)
Longitude
Longitude (centroid for polygon and line features)
radius (optional)
Radius of pointwise deposit site
BS sub-basin
HELCOM sub-basin of deposit site
Maintenance (Amount)
Amount material deposited, Maintenance dredging
Capital (Amount)
Amount material deposited, Capital dredging
Total amount
Total amount of material deposited
Unit
Unit of material deposited (e.g. tonnes - dry weight)
Amount (beneficial use)
Amount material deposited for beneficial use
Purpose (beneficial use)
Purpose of beneficial use